Cable Commissioning: Post-Installation Testing Tips

Cable laying process

The main purpose of post installation cable testing is to check the cable and accessories for any defects that may have occurred during the installation process. Should a defect be found, the techniques of after installation testing help pinpoint the place of the fault and repair it.

The steps to be performed during post installation testing depend on the requirements to the newly installed cable or cable system; they may include the insulation and conductor resistance tests, sheath and conductor phase identification, cross bonding test, sequence impedance measurements, serving tests to check the quality of the outer sheath, sheath or screen resistance tests, and HV tests.

This post is going to discuss what needs to be taken care of in the process of a cable system commissioning process. While being quite obvious, these steps are often ignored to speed up the test procedures, but failure to follow them is likely to result in injuries to the personnel and significant time loss due to resulting cable system downtime in future.

Safety comes first

Danger! Electrical hazard
Since power cable testing carries electrical hazard, it is crucial to ensure the safety of the staff involved and to prevent unauthorized access to the testing site. The people present at in the testing area are to be limited to the testing personnel, who should have an appropriate line of communication. The testing site should be fenced off and warning signs should be put up.

In addition to safety reasons, it is important to stay clear of potential interruption as, for instance, the undesirable actions of observers might compromise the testing results and lengthen the time of testing.

Abide by the industry standards and regulations

Codes for cabling installation and testing have been written for a reason and are a good source of safe, reasonable and efficient practice during cable system commissioning.

Discipline and experience to achieve accurate results

Cables under test should be properly deegenergized, with earthing applied before and after testing cable ends should be insulated and the necessary precautions should be taken to avoid accidental contact. Care should be taken to remove the semiconducting material of the oversheath so as to prevent a flashover while testing the sheath.

No short cuts should be taken, with sufficient amount of time allocated to remove all the cross bondings in the link boxes.

Have the right cable testing equipment at hand

To avoid any interruptions and delays in the testing process, it is important to have on site testing systems for cable diagnosis and fault location matching the tested cable system specification. The testing equipment should be properly calibrated and used by experienced personnel.

Having found a fault, double check

In case a defect has been found, it is necessary to discharge the cable and check the integrity of all cable connections. Following this, the testing procedure is repeated, and if the defect is confirmed, a time domain reflectometer (TDR) can be used for prelocation in conjunction with a fault pinpointing system to locate the exact place of the defect.
Cable testing and commissioning

Discharge properly

The modern cable testing equipment is typically supplied with a discharge feature. However, a safe testing practice requires a manual discharge, so using a discharge rod at the end of the cable testing process should never be neglected.

Alexei Tiatiushkin
Marketing manager
KharkovEnergoPribor Ltd.
marketing@keppowertesting.uk
http://www.kep.ua


http://news.chivindo.com/367/cable-commissioning-post-installation-testing-tips.html

Comments

Popular posts from this blog

SketchUp Pro 2020 v20.1.235 Full Version

BAGAS31 – SketchUp Pro 2020 v20.1.235 Full Version  merupakan software yang dirancang untuk membantu sobat membuat dan mengedit model 3D. Dengan desain tampilan yang ‘clean’ dan simple, menjadikan software ini mudah untuk digunakan. Software ini hadir dengan editor bawaan yang memungkinkan sobat mendesain objek 3D dari awal, Layout designer untuk menggabungkan model 3D serta Style Builder untuk menyesuaikan model dengan gaya yang berbeda. Software ini juga memiliki fitur untuk mengimpor data dari format lain, seperti 3DS, DWG, KMZ, JPG, PNG, PSD, TIF, TGA dan sebagainya. Tanpa berpanjang lebar, silakan download  Sketch Up Pro  versi terbaru 2020 v20.1.235 Full Version   melalui link yang disediakan. SketchUp Pro 2020 v20.1.235 Full Version Screenshots : Download : SketchUp Pro 2020 v20.1.235 Installer | Size: 128 MB [ FileUp ] | [ up4ever ] JAMU SketchUp Pro 2020 v20.1.235 Full Version | Size: 14.5 MB [ FileUp ] | [ ...

SCADA

SCADA merupakan singkatan dari Supervisory Control and Data Acquisitio n. SCADA merupakan sebuah sistem yang mengumpulkan informasi atau data-data dari lapangan dan kemudian mengirimkan-nya ke sebuah komputer pusat yang akan mengatur dan mengontrol data-data tersbut. Sistem SCADA tidak hanya digunakan dalam proses-proses industri, misalnya, pabrik baja, pembangkit dan pendistribusian tenaga listrik (konvensional maupun nuklir), pabrik kimia, tetapi juga pada beberapa fasilitas eksperimen seperti fusi nuklir. Dari sudut pandang SCADA, ukuran pabrik atau sistem proses mulai dar 1.000an hingga 10.000an I/O (luara/masukan), namun saat ini sistem SCADA sudah bisa menangani hingga ratusan ribu I/O. Ada banyak bagian dalam sebuah sistem SCADA. Sebuah sistem SCADA biasanya memiliki perangkat keras sinyal untuk memperoleh dan mengirimkan I/O, kontroler, jaringan, antarmuka pengguna dalam bentuk HMI (Human Machine Interface), piranti komunikasi dan beberapa perangkat lunak pendukung. Semua itu...

Persoalan Pokok pada Pembangkit Tenaga Listrik

Pembangkit listrik yang biasa digunakan pada suatu Sistem Tenaga Listrik (STL) terdiri dari pembangkit listrik tenaga air (Hydro plant atau PLTA) dan unit-unit thermal.Pembangkit-pembangkit itu sekarang ini umumnya sudah berhubungan satu dengan yang lainnya, atau yang sering disebut dengan interkoneksi. Setelah beroperasi dalam waktu tertentu, maka dari pembangkit-pembangkit itu ada yang keluar dari sistem interkoneksi dan hal ini disebabkan karena ada unit pembangkit yang rusak dan tentunya perlu diganti atau diperbaiki, kedua karena ada pembangkit yang istirahat untuk keperluan pemeliharaan. Salah satu contoh rencana pemeliharaan unit pembangkit adalah dengan menggunakan metode Levelized Resh dari Gaever . Namun dalam aplikasinya harus dibagi dalam dua kriteria, yaitu pertama unit pembangkit bisa dikeluarkan tanpa adanya penyesuaian. Kedua unit pembangkit yang dikeluarkan harus diatur dalam kurun waktu yang terbatas. Dengan demikian berarti pada waktu tertentu ada unit pembangkit y...

Jenis-jenis Plug dan Socket Listrik

Setelah pada artikel sebelumnya di sini yang membahas mengenai peralatan listrik rumah tinggal, maka artikel kali ini akan membahas lebih detail lagi mengenai satu peralatan instalasi listrik yang digunakan, yaitu plug dan socket. Plug dan socket listrik (dalam bahasa sehari-hari dikenal dengan colokan dan stop-kontak) 2 pin awalnya diciptakan oleh Harvey Hubbell dan dipatenkan pada tahun 1904. Karya Hubbell ini pun menjadi rujukan pembuatan plug dan socket setelahnya dan menjelang tahun 1915 penggunaannya semakin meluas, walaupun pada tahun-tahun 1920an peralatan rumah serta komersial masih menggunakan socket lampu jenis screw-base Edison. Kemudian plug 3 pin diciptakan oleh Albert Büttner pada tahun 1926 dan mendapatkan hak paten dari badan paten jerman (DE 370538), karyanya tersebut dikenal dengan nama "schuko" . Namun ada juga pencipta plug 3 pin ini, yaitu Philip F. Labre, semasa beliau masih menuntut ilmu di Sekolah Kejuruan Milwaukee (MSOE) dan mendapatkan hak paten d...

Autodesk SketchBook Pro 2021 Full Version

BAGAS31 – Sesuai dengan namanya, Autodesk SketchBook Pro 2021 Full Version ini merupakan software digital sketching atau drawing terbaik yang bisa kamu gunakan. Pada versi terbaru kali ini, ada beberapa penambahan fitur yang sangat efektif. Dengan fitur baru tersebut, diharapkan mampu meningkatkan proses sketching maupun drawing kamu. Autodesk SketchBook sendiri sudah bisa kamu dapatkan secara gratis melalui website resminya. Namun untuk kamu yang mau download versi Autodesk Sketchbook Pro, maka bisa langsung download melalui link yang sudah saya sediakan di bawah ini. Download Autodesk SketchBook Pro 2021 Full Version Screenshot: System Requirements: Windows 10 2.5 – 2.9 GHz of Intel or AMD CPU 4 GB of Memory 256 MB Graphics card with OpenGL 2.0 support We recommend that you use a pressure-sensitive tablet and pen for basic features Download: Autodesk SketchBook Pro 2021 Full Version [ FileUp ][ Uptobox ][ UsersDrive ] Jamu Only [ File...